Footprint
The Only US Company That Grows SiC Crystals and Builds Devices at Scale
Wolfspeed grows SiC in North Carolina and makes devices in New York, but most of its substrate becomes chips abroad.
- Made in US
- Made abroad
- Not disclosed
Wolfspeed is the only company in the US that grows SiC crystals, makes substrates and builds devices on them at scale. Its John Palmour plant in Siler City, North Carolina, grows the crystals and makes 200mm substrates. Its Mohawk Valley fab on the SUNY Polytechnic campus in Marcy, New York, the first 200mm SiC device fab in volume, makes every Wolfspeed MOSFET and diode since the Durham 150mm device fab closed in November 2025. Most of the substrate it sells goes to device makers in Europe and Asia.
The fab records are Siler City, Mohawk Valley and Durham. Substrate growth is covered on SiC Substrates.
Revenue and break-even
Wolfspeed Sells About Three-Quarters of Its Break-Even Revenue
| Quarter ended | Revenue | Detail |
|---|---|---|
| June 2025 | $197.0M | Quarter in which it filed for Chapter 11 |
| December 2025 | $168M | Mohawk Valley $76M; Materials $50M, down 44%; Power $118M including last-time buys from Durham |
| March 2026 | $150.2M | Refinanced $476M of first-lien debt; cash about $1.2B |
| June 2026 | $149.6M | Power $106.3M, Materials $43.3M; GAAP gross margin -25%; cash $1,088.6M |
| September 2026, guidance | $140M to $160M | Non-GAAP gross margin to stay negative; results due November 4, 2026 |
Wolfspeed told investors in August 2026 that it breaks even at about an $800 million annual revenue run rate, about $200 million a quarter, and that underused capacity at Mohawk Valley is the main cause of its negative margin. It now sells about three-quarters of that. Long-term debt was $931 million in June 2026, and its first-lien debt carries about 16% interest.
Defense loan
The Department of War Offered Up to $1.5 Billion Over 30 Years
On October 7, 2026, the Department of War's Office of Strategic Capital offered Wolfspeed a conditional loan of up to $1.5 billion with a 30-year term, in return for warrants on up to 7.5% of the company as the money is drawn. The loan is not final: it needs due diligence, definitive agreements, appropriations and consent from existing lenders.
- What it would fund: SiC materials and power devices, new or onshored GaN power device production, GaN epitaxy for communications and electronic warfare, GaN-on-SiC RF epitaxial wafers and radiation hardening.
- Where: the release names the North Carolina, New York and Arkansas sites.
- Why defense cares: GaN-on-SiC radar and electronic warfare modules, including Raytheon's SPY-6 and LTAMDS, depend on SiC substrates, and defense programs exclude Chinese SiC. Wolfspeed also signed a memorandum with GE Aerospace in fiscal 2026 for 10 kV SiC MOSFETs.
The loan would make the Department of War Wolfspeed's largest lender and a potential shareholder, which ties the largest Western SiC substrate supply to US defense policy. The CHIPS Act direct grant proposed in 2024 was never finalized; Wolfspeed received its CHIPS Act 48D tax credit instead.
Chapter 11
Chapter 11 Took 91 Days; Customers Took Their Second Sources With Them
Wolfspeed spent about $5 billion from fiscal 2022 to 2025 building 200mm SiC capacity in Siler City and Mohawk Valley. Demand came later and smaller than planned: EV sales slowed in 2023 and 2024, Tesla said in 2023 it would cut SiC content per vehicle, and Chinese substrates undercut Wolfspeed's prices. Revenue could not service $6.7 billion of debt.
Wolfspeed filed a prepackaged Chapter 11 in June 2025 and emerged on September 29, 2025, 91 days later, with debt cut by about $4.6 billion and annual interest down about 60%. Old shareholders kept 3 to 5% of the company, Robert Feurle took over as CEO, and deliveries continued throughout. Customers did not wait: automotive and industrial buyers qualified Infineon, STMicroelectronics and onsemi as second sources during the case, and that volume has not come back.
AI data center
AI Data Center Power Is the One Fast-Growing Market
AI data center power is the one market growing fast for Wolfspeed. Its data center revenue more than doubled in fiscal 2026 and rose about 20% from the March to the June quarter, from a small base. The company opened a data center team in Silicon Valley and named LITEON and Megmeet as power supply partners. NVIDIA's 800 V DC racks use SiC at the high-voltage conversion stages, which is the same reason EV inverters use it; that demand and its die counts are on SiC: Nine Markets, One Wafer and AI Data Center. Toyota is using Wolfspeed devices in an onboard charger.
China
Chinese Substrates Hold About a Third of the Market
SICC and TanKeBlue each held about 17% of SiC substrate revenue in 2024, against Wolfspeed's 33.7%, and Chinese substrates sold for about $400 a 6-inch wafer in 2025, well below Western prices. BYD Semiconductor, Sanan and CRRC build devices on Chinese substrates for Chinese EV and grid customers, so Wolfspeed's China sales are falling. Chinese SiC is not yet broadly qualified for Western automotive powertrains (IATF 16949, AEC-Q101), which keeps Infineon, STMicroelectronics and Rohm buying from Wolfspeed for now. Wolfspeed's longer answer is 300mm: it began shipping 300mm engineering samples in its fiscal fourth quarter of 2026.
Risks
Filling Mohawk Valley Decides Everything Else
| Risk | What drives it | Severity |
|---|---|---|
| Underused Mohawk Valley fab | Revenue about $150M a quarter against about $200M to break even | Critical |
| Permanent second-sourcing | Customers qualified Infineon, STMicroelectronics and onsemi during Chapter 11 | High |
| Chinese substrate prices | SICC and TanKeBlue together about a third of the market; Materials revenue falling | High |
| Defense loan not final | $1.5B needs definitive agreements, appropriations and lender consents | Medium |
| EV demand | Automotive SiC still soft in 2026 | Medium |
| Debt cost | First-lien debt at about 16%; net debt about $600M | Medium |
Record
Page Record
- Covers
- Wolfspeed sites and substrate customers, quarterly revenue and break-even, the Department of War loan offer, Chapter 11, AI data center power, Chinese competition and risks
- Sources
- Wolfspeed fourth-quarter fiscal 2026 release (SEC 8-K, August 2026) and call transcript via Benzinga; Wolfspeed release on the Office of Strategic Capital loan (SEC 8-K, October 7, 2026); PCIM Europe chip industry update (July 2026); TrendForce substrate shares (May 2025); prior SX Wolfspeed page for the December 2025 quarter and Chapter 11 terms; SX fab dataset (October 2026)
- Last verified
- October 2026