Funding and permits
Funding and Federal Permits Are Largely Settled
Two constraints that dominated 2023 and 2024 have mostly cleared. Commerce had awarded about $31.7 billion of the $35.5 billion in CHIPS direct funding by July 2026, 89% of it, and had paid out $13.1 billion by April 2026 (GAO). The Building Chips in America Act, signed in October 2024, exempts Commerce CHIPS financial assistance from National Environmental Policy Act (NEPA) review.
The exemption covers only Commerce's decision. Permits from other agencies still apply: Micron's plan to fill more than 200 acres of wetlands at Clay, New York still needed federal review, and the first fab there moved from 2028 to the third quarter of 2030. Award detail is at CHIPS and Science Act.
Power
Power Equipment Is Now the Longest Lead Item
A leading-edge fab draws 100 to 400 megawatts: TSMC Arizona phase 1 more than 100MW and Samsung Taylor more than 300MW at full buildout (reported). The large power transformers that step that load down from transmission voltage now take up to four years to deliver, longer than building the fab itself, and fabs order from the same factories as AI data centers. Grain-oriented electrical steel limits how fast transformer makers can add capacity. Power detail is at Power for Fabs and Fab Microgrids.
Tax credit
The Tax Credit Deadline Is the Next Cliff
The advanced manufacturing investment credit (Section 48D of the tax code) pays a share of the cost of fab buildings and tools. The 2025 reconciliation law (P.L. 119-21) raised it from 25% to 35% in July 2025, but it still applies only to fabs that begin construction before December 31, 2026. Fab phases that start later lose the credit unless Congress extends it, which makes the deadline the near-term limit on new US projects. Intel has said it may not build Intel 14A without an outside customer, and its Ohio fabs are now scheduled for 2030 to 2032 (Intel Foundry).
Workforce
People Remain the Slowest Constraint to Fix
A leading-edge fab needs 3,000 to 6,000 technicians, operators and engineers at steady state; TSMC expects about 6,000 in Arizona. Onondaga County officials cited labor shortages for the Micron Clay delay. CHIPS awards carry $293 million of workforce money across 13 of 19 final awardees (CRS), and the national workforce center planned under the National Semiconductor Technology Center ended when Commerce canceled the $7.4 billion Natcast award in August 2025.
Hiring from abroad is also uncertain. A September 2025 proclamation added a $100,000 fee to certain H-1B petitions; a federal court in Massachusetts blocked it on June 8, 2026 and the First Circuit kept the block in place on July 24, 2026, with the government's appeal still open. Programs and schools are at Workforce Hub.
Trade rules
Trade Rules Can Change Fab Costs Overnight
US fabs import most of their tools. The Section 232 proclamation of January 14, 2026 put a 25% tariff only on a narrow set of advanced computing chips, but it reserved broader tariffs on chips, chipmaking equipment and products that contain chips, with an offset for companies investing in US production. As of October 2026 that second phase has no date or rate. A tariff on imported tools would raise the cost of every US fab, since ASML is the only maker of EUV scanners (Wafer Fab Equipment).
Export controls cut the other way: they limit what US toolmakers can sell to China, which funds their R&D. The Bureau of Industry and Security (BIS) suspended its affiliates rule, which extends Entity List limits to companies 50% owned by listed firms, from November 10, 2025 to November 9, 2026. Polysilicon imports face a $21 per kilogram floor price from December 4, 2026 (Quartzite to Polysilicon).
All constraints
All Constraints, Ranked by Effect on Timing
The table orders constraints by how much they move US fab start dates in late 2026. Constraints that apply to every fab worldwide, such as EUV scanner supply, are ranked at the Bottleneck Atlas. Gigafactories and data centers compete for the same transformers, interconnects and electricians; the electrification view is on ElectronsX at Electrification Bottleneck Atlas.
- Eased
- Unchanged
- Tighter
| Constraint | What it limits | Status, October 2026 | Since 2024 | Relief |
|---|---|---|---|---|
| Large power transformers and switchgear | Substation energization for 100 to 400MW fab loads | Lead times up to four years for large power transformers (PwC, May 2026); fabs queue with AI data centers | Tighter | Low |
| Technicians and engineers | Ramp speed and second-phase timing | Micron cited labor shortages when it moved Clay from 2028 to 2030; $293M of CHIPS workforce money across 13 of 19 awardees | Unchanged | Low to medium |
| Section 48D tax credit deadline | Whether a new fab gets a 35% investment credit | Credit raised from 25% to 35% in July 2025 but only for fabs that begin construction by December 31, 2026 | Tighter | Needs Congress |
| Grid interconnection | Site selection and first power | Interconnect studies run 12 to 24 months in ERCOT and Arizona service areas (reported); fabs share queues with data centers | Unchanged | Low to medium |
| Trade rules on chips and tools | Cost of imported tools and parts | Section 232 phase one (January 15, 2026) is narrow; broader tariffs on chips and fab tools are reserved with no date; polysilicon floor price from December 4, 2026 | Tighter | Low |
| Export controls | Toolmaker revenue and compliance cost | BIS affiliates rule suspended November 10, 2025 to November 9, 2026; snapback expected without further action | Tighter | Low |
| Skilled immigration | Hiring experienced fab engineers from Taiwan, Korea and Japan | $100,000 H-1B fee (September 2025) blocked in court since June 8, 2026; appeal pending | Unchanged | Low |
| Water rights | Ultrapure water supply in Arizona and Texas | Negotiated site by site; TSMC Arizona targets more than 90% reclamation | Unchanged | Medium |
| Imported tools and materials | Every fab, wherever it is | EUV scanners only from ASML; EUV resist and ABF substrate film from Japan; see the Bottleneck Atlas | Unchanged | Low |
| Federal environmental review (NEPA) | Federal funding decisions | Building Chips in America Act (October 2024) exempts Commerce CHIPS assistance; other agencies' permits, such as wetlands fill, still apply | Eased | Done in part |
| CHIPS funding | Project financing | About $31.7B of $35.5B in direct funding awarded (89%); $13.1B paid out as of April 2026 | Eased | Mostly done |
Record
Page Record
- Covers
- Constraints on building and running US fabs: funding, environmental review, power equipment, interconnection, tax credit timing, workforce, immigration, trade rules, export controls, water and imported tools
- Sources
- GAO-26-109121 (August 6, 2026); Congressional Research Service R49031 (July 14, 2026); Building Chips in America Act, P.L. 118-105 (October 2024); P.L. 119-21, Section 70308 (July 2025); White and Case on Proclamation 11002 (January 2026); ARMA International Trade Sentinel (Q3 2026); Willkie Farr on the BIS affiliates rule (September 2026); PwC via PV Magazine (May 2026); University of Colorado ISSS on the H-1B fee (October 7, 2026). Power draw and interconnect durations carried from the previous page as reported.
- Last verified
- October 2026