Inside the rack
A Vera Rubin Rack Holds 108 Processors and 20.7 TB of HBM4
The unit of AI data center purchasing is now the rack, not the server, and its contents are set by NVIDIA.
NVIDIA's Vera Rubin NVL72 is the rack most 2026 and 2027 AI campuses are being built around. It was ramping into full production by August 2026, with racks running at CoreWeave, Google Cloud, Microsoft Azure, Oracle Cloud Infrastructure and Nebius. The platform has seven chip designs: the Rubin GPU, the Vera CPU, the Groq 3 LPU, the NVLink 6 switch, the ConnectX-9 SuperNIC, the BlueField-4 DPU and the Spectrum-6 Ethernet switch.
| Part | Count per rack | Made by | Where |
|---|---|---|---|
| Rubin GPU | 72 | TSMC N3P logic, HBM4 from three memory makers, TSMC CoWoS-L | Taiwan and Korea |
| Vera CPU | 36 | TSMC | Taiwan |
| HBM4 | 20.7 TB in total | SK hynix, Samsung, Micron | Korea, Japan, Taiwan |
| NVLink 6 switch | 9 switch trays | TSMC | Taiwan |
| ConnectX-9 SuperNIC | 8 per compute tray | TSMC | Taiwan |
| Power shelves and 800 V conversion | Per rack design | Delta, LITEON, Flex; SiC and GaN from Infineon, Navitas, onsemi and others | Taiwan, Southeast Asia, US |
The rack draws about 190 kW in its Max Q setting and about 230 kW in Max P. The full set of suppliers behind each Rubin GPU, from wafer to final test, is on the NVIDIA Rubin supplier ring; the rack-level ring, including power and cooling, is on DatacentersX.
Who makes it
Every Compute Chip in the Rack Comes From TSMC
- Made in US
- Some US volume
- US planned
- Made abroad
Every compute chip in the rack is made by TSMC, and every GPU is packaged on TSMC CoWoS-L. The HBM comes from three memory makers, all outside the United States. Nothing in the compute path has a second foundry.
- Logic: TSMC N3P for Rubin; NVIDIA's earlier Blackwell Ultra B300 logic die is the only AI accelerator part in the site's 80-row supplier dataset already made in the US at volume, at TSMC Fab 21 in Phoenix. See Leading-Edge Fabs.
- HBM: the memory makers' share, the base die and the 12-high stacks are on HBM.
- Packaging: NVIDIA holds nearly 60% of 2026 CoWoS supply; capacity and the Arizona plan are on CoWoS.
Per gigawatt
A Gigawatt Holds About 380,000 Rubin GPUs
Operators now announce AI campuses in gigawatts, and NVIDIA prices its opportunity the same way. On its August 2026 earnings call NVIDIA put its revenue at about $40 billion per gigawatt for Vera Rubin, against about $25 billion for Grace Blackwell and about $18 billion for Hopper. Jensen Huang also said the cost of a gigawatt of data center technology had risen from about $30 billion five years ago to about $60 billion.
| Category | Share of spend | Main chip content |
|---|---|---|
| Compute | 39% | GPUs and CPUs with their HBM; about $13.7B of a $35B gigawatt (computed) |
| Networking | About 13% | Switch ASICs, NICs, retimers, optical transceivers and their lasers |
| Mechanical and electrical | About a third | Power conversion, UPS and drives: SiC, GaN and silicon power devices; controllers |
| Generators and turbines, inside the above | About 6% | Control electronics only |
| Transformers, inside the above | About 5% | Few chips today; solid-state transformers add SiC |
| Foundry, memory and wafer equipment share | About 3 to 4% | What chipmakers and toolmakers capture, about $1 to 1.2B a gigawatt |
Bernstein's November 2025 estimate put a gigawatt at about $35 billion; NVIDIA's own figure is $50 to $60 billion. The two disagree mainly on how much of the GPU price to count. Both put more than half the spend into chips and the systems built around them.
Power chips
800 Volt Racks Pull SiC and GaN Into the Data Center
Rack power has gone from about 40 kW for an air-cooled server rack to 190 to 230 kW for Vera Rubin, and NVIDIA's Kyber rack for Rubin Ultra, due in 2027, holds 576 GPUs and targets 1 MW. AMD's Helios rack of 72 GPUs runs about 225 to 245 kW; rack figures for each accelerator are on the DatacentersX AI Chip Layer page. At that density the 415 or 480 V AC used in data centers today needs more copper than fits, so NVIDIA is moving its partners to 800 V DC, which carries more than 150% more power through the same copper.
- Silicon partners named by NVIDIA: Analog Devices, AOS, EPC, Infineon, Innoscience, MPS, Navitas, onsemi, Power Integrations, Renesas, Richtek, ROHM, STMicroelectronics and Texas Instruments.
- Power content: Infineon estimates $100 to $250 of power semiconductors per kW of installed AI compute, and targets EUR 1.5 billion of AI data center power revenue in its current fiscal year, rising to EUR 2.5 billion in fiscal 2027.
- SiC and GaN: 800 V conversion uses silicon carbide at the high-voltage stages and gallium nitride closer to the board. Wolfspeed's AI data center revenue more than doubled in its fiscal 2026. Die counts and substrate supply are on SiC: Nine Markets, One Wafer.
US production
US AI Campuses Run on Chips Made in Taiwan and Korea
- Made in US
- Some US volume
- US planned
- Made abroad
| Part | US site | Status | US status |
|---|---|---|---|
| Blackwell Ultra B300 logic die | TSMC Fab 21, Phoenix, Arizona | In volume; the one US-made row of 80 in the site's AI chip supplier dataset | Made in US |
| Rubin-class logic (N3) | TSMC Arizona second fab | N3 production from 2027 | US planned |
| CoWoS-class packaging | Amkor, Peoria, Arizona; TSMC Arizona packaging | Amkor from early 2028; TSMC before 2029 | US planned |
| Final test | KYEC US sites, prepaid by NVIDIA | Sites not disclosed | US planned |
| HBM4 | None; SK hynix packaging plant in West Lafayette, Indiana planned for 2028 | Korea, Japan and Taiwan today | Made abroad |
| Optical lasers | Coherent, Sherman, Texas (6-inch InP) | Operating and expanding | Some US volume |
| Rack assembly | Foxconn, Wistron and others in Texas | Ramping; most racks still built in Mexico and Taiwan | Some US volume |
Meta raised its 2026 capital spending guidance to $125 billion to $145 billion in April 2026, and the four largest US cloud companies together were reported above $700 billion for the year. Almost all of the compute in those campuses is fabricated, stacked and packaged in Taiwan and Korea. The US share is rising from logic outward: wafers in Arizona now, packaging from 2028 and memory later. US fab status is tracked on US Reshoring.
China
China Builds Its AI Data Centers on Huawei and SMIC
Chinese AI data centers run on a separate stack. US export rules keep NVIDIA's leading GPUs out, and Chinese buyers have been told to favor domestic chips, so Huawei's Ascend 910C and its successors, built by SMIC on 7nm-class processes with stockpiled HBM, carry most new Chinese training capacity. China's AI campuses face the reverse constraint: power is cheap and plentiful, chips and HBM are not. That supply chain is on Huawei and HiSilicon and China Bifurcation.
Record
Page Record
- Covers
- Vera Rubin NVL72 rack contents, chip suppliers and locations, chip content and capital spend per gigawatt, 800 V power semiconductors, US production status and China
- Sources
- NVIDIA Vera Rubin NVL72 specifications via Hashrate Index (March 2026); NVIDIA fiscal 2Q27 call via Magica (August 2026); Bernstein via Investing.com (November 2025); Data Center Dynamics on 800 V DC (October 2025); PCIM Europe chip industry update (July 2026, Infineon figures); Yahoo Finance on 2026 capex (May 2026); SX chip supplier ring dataset (October 2026)
- Last verified