Inside a tool
Every Fab Tool Is Built From Parts Few Companies Make
Toolmakers integrate subsystems from specialist suppliers, and those suppliers set how fast tools can ship.
A fab buys tools, and each tool is an assembly of subsystems bought from a second tier of suppliers. Those subsystems carry chips of their own: power transistors in RF generators, FPGAs and processors in controllers, sensor chips in flow and pressure meters. When AI demand filled fabs in 2026, toolmakers found that their own parts, not their factories, set how fast they could ship.
- Some US volume
- Made abroad
- Not disclosed
The chamber wear parts that a tool burns through, such as silicon rings, quartz and showerheads, are on Fab Process Consumables. The tool market itself is on Wafer Fab Equipment.
RF power
Three Companies Make Most RF Power Supplies for Chip Tools
Every plasma etch and plasma deposition chamber is driven by an RF generator and a matching network that tunes its power into the plasma. Leading-edge etch uses several generators per chamber at different frequencies, pulsed in microseconds. Three companies, MKS Instruments, Advanced Energy and Comdel, make 65 to 75% of the world's RF power supplies for chip tools, and Comet of Switzerland and Japan's Kyosan and Daihen make most of the rest.
| Company | Headquarters | Latest figure | Period |
|---|---|---|---|
| Advanced Energy | Denver, Colorado | Semiconductor equipment revenue $278.3M, up 33% | Quarter ended June 2026 |
| MKS Instruments | Andover, Massachusetts | Semiconductor revenue about $554M, up 28% (reported) | Quarter ended June 2026 |
| Comet | Flamatt, Switzerland | Group net sales CHF 155.6M, up 51.9%, led by plasma control | Quarter ended September 2026 |
| Comdel | Gloucester, Massachusetts | Private; no figures published |
Comet is ramping a new plant in Penang, Malaysia, and Advanced Energy's inventory rose about 30% in the first half of 2026 as it built ahead of demand. The MKS figure is from a secondary summary of its filing and is marked reported.
Lead times
RF Power Supplies Now Take 24 Months
| Item | Lead time | Before | Source |
|---|---|---|---|
| Imported RF power supplies | 24 months | Not stated | TrendForce, August 2026 |
| High-end packaging and test tools | More than 18 months | Not stated | TrendForce, August 2026 |
| Conventional etch and deposition tools | About 12 months | About 6 months | TrendForce, August 2026 |
| Deposition tool parts, one Korean toolmaker | Up to 10 months | 4 months | ETNews, September 2026 |
| Japanese parts for one laser tool maker | Up to 40 months | Not stated | ETNews, September 2026 |
| AMEC etch tools (China) | About 9 months | TrendForce, August 2026 | |
| Piotech CVD tools (China) | About 10 months | TrendForce, August 2026 |
Toolmakers told ETNews that their part suppliers had not added capacity ahead of the AI surge, and that paying a premium did not move deliveries forward. The longest waits are for subsystems built by a few specialist makers: RF power, precision optics and vacuum hardware.
Controllers
Tool Controllers Wait on the Same Chips as AI Servers
A tool's controllers run motion stages, gas sequencing and fault detection, and many use FPGAs because they can be reprogrammed in the field and kept in production for decades. In mid-2026 lead times on AMD's Versal and UltraScale FPGAs ran 40 to 52 weeks or more, with some older parts quoted at 300 to 364 days, according to the distributor Fusion Worldwide. AI servers take first call on the same foundry capacity.
In the 2021 chip shortage ASML and other toolmakers reported that missing chips held back tool shipments, so a chip shortage slowed the tools that would have ended it. The same loop now runs through RF generators and FPGAs instead of microcontrollers.
China
China Makes a Third of Its Tools but a Fifth of Their RF Power
China's own toolmakers supplied about 35% of the equipment installed in Chinese fabs in 2025, up from about 25% in 2024, according to China's National Development and Reform Commission, which set a 70% target for 2027. The parts inside those tools lag behind:
- RF power supplies: about 20% made in China, mostly for mature-process tools.
- Precision vacuum valves: under 10% for high-end chamber valves; VAT Group of Switzerland holds 60 to 70% of the world market.
- Quartz parts: 30 to 40% made in China.
A Chinese etch tool from AMEC or NAURA can therefore still carry a US-made RF generator and a Swiss valve. Shorter lead times are AMEC's selling point while Western tools wait 12 months or more. China's tool push is on China Bifurcation.
The fab building
The Fab Building Runs on Power Semiconductors
The fab building is a chip customer too. A leading-edge fab draws hundreds of megawatts through transformers, switchgear and uninterruptible power supplies built on IGBT and SiC power devices; its chillers, pumps and fans run on variable-speed drives; and thousands of sensors feed its control systems. Fab power is covered on Fab Power and Fab Microgrids, and the SiC devices in UPS and drives on SiC: Nine Markets, One Wafer.
Record
Page Record
- Covers
- Tool subsystems and their suppliers, RF power supplies, 2026 lead times, controller FPGAs, China's localization of tool parts and fab facility power semiconductors
- Sources
- TrendForce News (equipment lead times, August 19, 2026); ETNews via XenoSpectrum (part lead times, September 2026); Tech Times (China localization, August 29, 2026); Advanced Energy second-quarter 2026 release; MKS second-quarter 2026 via Panabee (reported); Comet third-quarter 2026 trading update (October 20, 2026); Fusion Worldwide (FPGA lead times, July 2026)
- Last verified
- October 2026